Audited and installed power cable lines.
- power lines were installed in 6 meeting rooms above the ceiling (for connecting a projector and Apple TV) and under the tables;
- laying more than 1 km of cable products;
- installation of cable channels in Open Space for 44 workplaces;
- viewed by 184 Schneider power outlets;
- cable channels are laid and fixed on asbestos fabric;
- differential circuit breakers installed in electrical panels;
- installation of external power outlets in the accounting department and kitchen completed;
- video intercom installed;
- mounted and switched pendant lights;
- After the completion of the installation work, measuring measures were taken.
Result: the work was done professionally and efficiently, within the time allotted by the contract.